Question: QS 1 7 - 1 2 ( Static ) Allocating overhead cost using activity - based costing LO P 3 Rand Company computed the following

QS 17-12(Static) Allocating overhead cost using activity-based costing LO P3
Rand Company computed the following activity rates using activity-based costing.
\table[[Activity,Activity Rate],[Setup,$1,000 per setup],[Materials handling,$50 per materials requisition],[Inspection,$2 per unit inspected]]
The company's deluxe model used the following activities to produce 1,000 units.
Activity
Setup
Materials handling
Inspection
Actual Activity Usage
3 setups
25 materials requisitions
1,000 units inspected
Compute the overhead cost per unit for the deluxe model using activity-based costing.
\table[[Activity,,,,Allocated Cost],[Setup,,,,],[Materials handling,,,,],[Inspection,,,,],[Total allocated cost,,,,],[Units produced,,,,],[Overhead cost per unit,,,,]]
 QS 17-12(Static) Allocating overhead cost using activity-based costing LO P3 Rand

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!