Question: Quantity: 1 2 0 0 lb Production rate: 0 . 2 0 MH / lb Number of crews: 4 Productivity factor: 7 5 % productivity
Quantity: lb
Production rate: MHlb
Number of crews:
Productivity factor: productivity operate at capacity
Using this information, what is the estimated duration days