Question: QuesLIULIJ Illdl KSI Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. a. Draw the precedence diagram for

QuesLIULIJ Illdl KSI Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. a. Draw the precedence diagram for the set of tasks. b. Calculate the minimum number of workstations. c. Show what tasks are assigned to which stations? Using the heuristic rules d. How much idle time is there, summed over all workstations? e. What is the efficiency of this line? Immediate Predecessor(s) Work Task 1 Task Time (seconds) A 70 B 60 C 120 DT E 240 L F 100 G 190 A B CD A EF