Question: Question 0 2 : Use the following product structure tree to develop the MRP plan for the components A and B . Finished product x

Question 02:
Use the following product structure tree to develop the MRP plan for the components A and B. Finished product x will be shipped 100 quantities at the start of week 6 and 90 quantity at the start the week 7. One case of A (50 units in one case) is scheduled at week 4,5,6,7 and One case of B(30 units in one case) is scheduled at week 5,6. There are 30 units of A and 10 units of B now on hand. Lead time for all the components is one week.
Solution:
\\table[[Week,1,2,3,4,5,6,7],[Quantity,,,,,,100,90]]
\\table[[A,Gross Requirements,,,,,200,180,],[LT=1wk,Scheduled Receipts,,,,50,50,50,50],[Lot size,Projected on hand,30,30,30,80,130,80,50],[50 units,Net Requirements,,,,,70,100,],[Planned order reccipts,,,,,100,100,],[Planned order releases,,,,100,100,,]]
\\table[[B,Gross Requirements,,,,,300,270,],[LT=1wk,Scheduled Receipts,,,,,30,30,],[Lot size,Projected on hand,10,10,10,10,40,40,10],[30 units,Net Requirements,,,,,260,230,],[Planned order reccipts,,,,,270,240,],[Planned order releases,,,,270,240,,]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!