Question: Use the following product structure tree to develop the MRP plan for the components A and B . Finished product X will be shipped 1

Use the following product structure tree to develop the MRP plan for the components A
and B. Finished product X will be shipped 110 quantities at the start of week 6 and 100
quantity at the start the week 7. One case of A (50 units in one case) is scheduled at
week 4,5,6,7 and One case of B (30 units in one case) is scheduled at week 5,6.
There are 30 units of A and 10 units of B now on hand. Lead time for all the
components is one week.
 Use the following product structure tree to develop the MRP plan