Question: Question 1 0 ( 1 point ) Saved A project is consist of 5 activities. The durations and interdependencies of the activities are shown in
Question point
Saved
A project is consist of activities. The durations and interdependencies of the activities are shown in the following table. What is the slack of activity E
Enter your answer in the box as a whole number. For example, if your answer is days, enter the number in the box.
Duration Immediate predecessor
A days
B days
C days
D days A
E days B
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
