Question: Question 1 0 ( 1 point ) Saved A project is consist of 5 activities. The durations and interdependencies of the activities are shown in

Question 10(1 point)
Saved
A project is consist of 5 activities. The durations and interdependencies of the activities are shown in the following table. What is the slack of activity E?
Enter your answer in the box as a whole number. For example, if your answer is 2 days, enter the number 2 in the box.
Duration Immediate predecessor
A 10 days -
B 9 days -
C 6 days -
D 2 days A
E 3 days B

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!