Question: Question 2 1 ( 1 point ) Saved A project is consist of 5 activities. The durations and interdependencies of the activities are shown in

Question 21(1 point)
Saved
A project is consist of 5 activities. The durations and interdependencies of the activities are shown in the following table. What is the slack of activity B?
Enter your answer in the box as a whole number. For example, if your answer is days, enter the number 2 in the box.
\table[[,Duration,Immediate predecessor],[A,10 days,-],[B,9 days,-],[C,6 days,-],[D,2 days,A],[E,3 days,B]]
Your Answer: