Question: QUESTION 1 0 Table 7 . 9 table [ [ , TIME ( WEEKS ) , COST ( $ ) ] , [ ACTIVITY

QUESTION 10
Table 7.9
\table[[,TIME (WEEKS),COST ($)],[ACTIVITY,\table[[IMMEDIATE],[PREDECESSOR(S)]],NORMAL,CRASH,NORMAL,CRASH],[A,--,3,2,3,000,3,300],[B,---,6,4,8,000,9,000],[C,A,1,1,4,000,4,000],[,,,,,],[D,A,5,4,3,500,4,000],[E,B,4,3,4,750,5,500],[F,C,2,2,2,000,2,000],[,,,,,],[G,D,1,1,4,000,4,000],[H,D,F,3,2,3,500,3,750],[I,E,G,3,2,3,000,4,250],[J,E,2,1,5,000,7,000]]
Using Table 7.9, if the project's normal earliest completion time is to be reduced by two weeks, what is the minimum additional reduction?
greater than $2,000
less than or equal to $1,000
greater than $1,000 but less than or equal to $1,500
greater than $1,500 but less than or equal to $2,000
 QUESTION 10 Table 7.9 \table[[,TIME (WEEKS),COST ($)],[ACTIVITY,\table[[IMMEDIATE],[PREDECESSOR(S)]],NORMAL,CRASH,NORMAL,CRASH],[A,--,3,2,3,000,3,300],[B,---,6,4,8,000,9,000],[C,A,1,1,4,000,4,000],[,,,,,],[D,A,5,4,3,500,4,000],[E,B,4,3,4,750,5,500],[F,C,2,2,2,000,2,000],[,,,,,],[G,D,1,1,4,000,4,000],[H,D,F,3,2,3,500,3,750],[I,E,G,3,2,3,000,4,250],[J,E,2,1,5,000,7,000]] Using Table 7.9, if

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!