Question: Part 1 Exercise Questions exercise questions 1 , 3 , 5 , 6 and 9 found at the end of Chapter 8. Part 2 Scheduling
Part 1 Exercise Questions
exercise questions 1 , 3 , 5 , 6 and 9 found at the end of Chapter 8.
Part 2 Scheduling Problem
Complete the following:
Your child is a member of the school theater group and have been asked to prepare the schedule, etc. for a skit to be performed during the 4th of July celebration in the local village square. As a volunteer, you offer to serve as the project controller because of your expertise in schedule management.
- Construct an AON diagram similar to the format used in the Youtube videos found in the commentary using an MS Excel spreadsheet. Ensure that you include a Start activity and a Finish activity. Include a legend (example is the one completed in Question 1, Part 1.
- Calculate the estimated time for each activity using PERT techniques for the 3 estimates provided. Include a sample calculation.
- make table that identifies all paths and their lengths. Which path is the critical path?
- During the execution phase of the skit project, one of the activities on the critical path is delayed by one day. Is this serious?
- Using the activity estimates for optimistic, pessimistic and most likely time to complete activities on the critical path, qualitatively discuss the estimate uncertainty of the critical path.
| Activity | Predecessor | Time (days) | ||
| Optimistic | Most Likely | Pessimistic | ||
1 | None | 2 | 4 | 6 |
2 | None | 5 | 5 | 5 |
3 | 2 | 3 | 5 | 7 |
4 | 1 | 7 | 10 | 13 |
5 | 1 | 11 | 12 | 13 |
6 | 2,4 | 5 | 6 | 7 |
7 | 3 | 9 | 10 | 11 |
8 | 3,6 | 5 | 7 | 9 |
9 | 4 | 7 | 9 | 11 |
10 | 5 | 3 | 3 | 3 |
11 | 7 | 15 | 17 | 19 |
12 | 8 | 6 | 8 | 10 |
13 | 9,10 | 7 | 8 | 15 |
14 | 7 | 12 | 14 | 16 |
15 | 12,13 | 16 | 17 | 18 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts