Question: Question 1 0 The following table shows a project plan: table [ [ Activity , Duration ( weeks ) , Predecessor ] , [
Question
The following table shows a project plan:
tableActivityDuration weeksPredecessorABACADBECD
The critical path is:
Enter the critical path with activities separated by Eg ABCDE
Even if Canvas marks this wrong, you may have the right answer. I will fix it when grac
The project duration is: weeks.
Enter a number without any decimal places.
This question is considered a problem based question you can include this problem in upload. In order receive credits you must clearly show the ES EF LS LF and slack.