Question: Question 1 ( 1 0 points ) Place these activities into the correct sequence. Staging and Layout Design Development Commissioning Assigning the Project Team Bidding

Question 1(10 points)
Place these activities into the correct sequence.
Staging and Layout
Design Development
Commissioning
Assigning the Project Team
Bidding
Programming and Feasibility
Owner Occupation
Punch-out
Construction
 Question 1(10 points) Place these activities into the correct sequence. Staging