What should Kira do Select all that apply.
Offer to do some of Bryan's work in exchange for some studio time
Show Bryan her project schedule and ask for his help solving this scheduling conflict
Ask Bryan about his project to see if it's more important than hers
Bring Bryan his favorite coffee and ask if he'd give her some of his studio time
Ask Bryan if there's a way to schedule studio time for both projects
Formally ask their supervisors for help solving the conflict