Question: Question 1 (1 point) The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and

Question 1 (1 point) The demand for subassembly S
Question 1 (1 point) The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Given the data below, how many units of U would be required to have to be ordered in week 3? (enter your number as a number; (example 12 not twelve) S 2 LFL 0 0 Item Lead Time Lot Size SS POH Scheduled Receipts T 1 1 0 1000 U 2 100 25 25 500 in wk1 A/