Question: Question 1 ( 1 point ) The project has reasonable access to the entire reservoir of technology in all functional divisions in a matrixed organization

Question 1(1 point)
The project has reasonable access to the entire reservoir of technology in all functional divisions in a matrixed organization
Question 1 options:
True
False
Question 2(1 point)
Which organizational structure has the highest availability of resources
Question 2 options:
weak matrix
projectized
strong matrix
functional
Question 3(1 point)
Project priorities cause more conflict at which stage of a project life cycle
Question 3 options:
late
final
early
middle
Question 4(1 point)
In the Agile approach to projects, this individual works with clients to gain a clear understanding of their needs
Question 4 options:
scrum master
product owner
developer
client
Question 5(1 point)
The choice of organization structure for the project team is made by the project manager
Question 5 options:
True
False
Question 6(1 point)
The organizational structure that has both functional and projectized divisions coexisting in an firm is
Question 6 options:
encompassing
composite
objective
free form
Question 7(1 point)
There is minimal flexibility in the use of staff with a functional organization
Question 7 options:
True
False
Question 8(1 point)
The process of dealing with uncertainty in projects that may affect the project for better or for worse is known as
Question 8 options:
procurement management
risk management
quality management
scope management
Question 9(1 point)
In a projectized organization, the project manager shares authority with functional managers
Question 9 options:
True
False
Question 10(1 point)
This behaviour in a project manager is highly correlated with unsuccessful projects
Question 10 options:
conflict avoidance
win-win negotiation techniques
interdisciplinary problem solving
risk mitigation
Question 11(1 point)
The project office serves this main purpose
Question 11 options:
a central location of all project clerical support
critical disaster recovery support
maintaining a project management library
a link between strategic management goals and project management goals
Question 12(1 point)
As long as the organizational structure is sufficient to the tasks imposed on it, the structure tends to remain the same
Question 12 options:
True
False

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!