Question: Question 1 1 pts Activities K, M, N and Simmediately follow activity H, and their latest finish times are 14, 18, 12 and 12. The

Question 1 1 pts Activities K, M, N and

Question 1 1 pts Activities K, M, N and Simmediately follow activity H, and their latest finish times are 14, 18, 12 and 12. The latest finish time for activity H... O is 14. is 12 cannot be determined from the information provided is 18