Question: Question Content AreaActivities K , M , and S immediately follow activity H , and their latest start times are 1 4 , 1 8

Question Content AreaActivities K, M, and S immediately follow activity H, and their latest start times are 14,18, and 11. The latest finish time for activity H
a. is 18.
b. is 11.
c. is 14.
d. Cannot be determined.