Question: Question 1 1 Risks can be prioritized based onIthe likelihood of occurrence and degree of impact.Bthe amount of time the project team has to manage

Question 11Risks can be prioritized based onIthe likelihood of occurrence and degree of impact.Bthe amount of time the project team has to manage the risk.* the amount of funds planned to manage the risk.D the project team member that identified the risk.