Question: Risks can be prioritized based on 1 ) the likelihood of occurrence and degree of impact . 2 ) the project team member that identified

Risks can be prioritized based on1) the likelihood of occurrence and degree of impact.2) the project team member that identified the risk.3) the amount of time the project team has to manage the risk.4) the amount of funds planned to manage the risk.