Question: QUESTION 1: [10 POINTS] Find the LST, LFT, EFT, EST, Critical Path and the Slack for the below table through drawing the notation of PERT/CPM?

QUESTION 1: [10 POINTS] Find the LST, LFT, EFT,

QUESTION 1: [10 POINTS] Find the LST, LFT, EFT, EST, Critical Path and the Slack for the below table through drawing the notation of PERT/CPM? Predecessors Activity A Time (days) 6 B A B D N 1 E F DE G E,F 4 H G 6 1 D,G 8