Question: Question 1 (10 points) What would be the change in Makespan if the patients were sequenced using Johnson's Rule instead of sequencing them in the
Question 1 (10 points)
What would be the change in Makespan if the patients were sequenced using Johnson's Rule instead of sequencing them in the current order.
| Patient | Preparation | Procedure |
| A | 2.5 | 2.8 |
| B | 2.7 | 3.0 |
| C | 2.8 | 1.1 |
| D | 1.6 | 1.8 |
| E | 2.2 | 2.6 |
Question 1 options:
|
| Makespan would decrease 1.3 |
|
| Makespan would decrease 1.7 |
|
| Makespan would decrease 1.1 |
|
| Makespan would decrease 1.5 |
Question 2 (10 points)
If you have 5 jobs and you do not change the sequence, what will be the average flowtime for all 5 jobs?
| Job | Processing Time | Days Due from Today |
| A | 8 | 11 |
| B | 32 | 19 |
| C | 28 | 25 |
| D | 26 | 19 |
| E | 37 | 19 |
Question 3 (10 points)
You work for a dentist that has 5 patients to perform procedures on. What would be the sequence that you would work on these patients if you used Johnson's Rule?
| Patient | Preparation | Procedure |
| A | 2.1 | 2.8 |
| B | 2.7 | 2.5 |
| C | 2.8 | 1.1 |
| D | 1.6 | 1 |
| E | 2.2 | 2.3 |
Question 3 options:
|
| A,B,E,C,D |
|
| A,E,B,C,D |
|
| B,D,A,E,C |
|
| D,E,A,B,C |
|
| B,A,E,D,C
|
You have 5 jobs to process. What is the makespan if you do them in the current order?
| Job | Processing Time | Days Due from Today |
| A | 16 | 24 |
| B | 22 | 30 |
| C | 6 | 13 |
| D | 8 | 28 |
| E | 18 | 17 |
Question 4 options:
|
| 80 |
|
| 70 |
|
| 89 |
|
| 83 |
|
| 79 |
Question 5 (10 points)
You have 5 jobs to process. If you process them in the current order, what will be the average tardiness for the five jobs?
| Job | Processing Time | Days Due from Today |
| A | 7 | 27 |
| B | 37 | 24 |
| C | 14 | 13 |
| D | 13 | 34 |
| E | 28 | 31 |
Step by Step Solution