Question: Question 15 (3.03 points) What would be the change in Average Tardiness if you performed the following five tasks using Earliest Delivery Date instead of

Question 15 (3.03 points)

What would be the change in Average Tardiness if you performed the following five tasks using Earliest Delivery Date instead of completing them in the current sequence?

Job Processing Time Days Due from Today
A 20 24
B 23 15
C 22 40
D 14 28
E 10 16

Question 15 options:

Lowers average tardiness by 7.0

Lowers average tardiness by 9.0

Lowers average tardiness by 7.2

Lowers average tardiness by 11.6

Lowers average tardiness by 6.6

Question 16 (3.03 points)

What is the Linear Regression Forecast for Month 10 using the data below?

Month 1 Month 2 Month 3 Month 4 Month 5 Month 6
Demand 13 15 12 18 19 21

Question 16 options:

32.1

24.7

27.1

25.6

26.4

Question 17 (3.03 points)

What would be the change in Makespan if the patients were sequenced using Johnson's Rule instead of sequencing them in the current order.

Patient Preparation Procedure
A 2.5 2.8
B 2.7 3
C 2.8 1.1
D 1.6 1
E 3.6 2.6

Question 17 options:

Makespan would decrease 1.6

Makespan would decrease 1.3

Makespan would decrease 1.8

Makespan would decrease 1.1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!