Question: Question 1: (17 marks) The data given in Table 1 shows PV, EV, and AC values in thousands of dollars for the first 30 weeks

Question 1: (17 marks)

The data given in Table 1 shows PV, EV, and AC values in thousands of dollars for the first 30 weeks of a projects execution before its completion. Answer the following questions:

a. Using three different pen colors, draw a graph showing the curves PV, EV, and AC. Label appropriately the curves and the x-axis and y-axis (5 marks);

b. Indicate the intervals of time where the project is on schedule, going faster or slower than the planned schedule (4 marks);

c. Indicate the intervals of time where the project is on budget, under or over the planned budget (4 marks);

d. Evaluate the budget gain or loss that occurred on week 15 in dollars (2 marks);

e. Evaluate the schedule status on week 25 (2 marks).

Activity

ID

Week

Number

PV $(000)

EV $(000)

AC $(000)

A

5

7

5

2

B

10

13

10

7

C

15

18

15

12

D

20

20

20

20

E

25

22

25

28

F

30

27

30

33

Question 2: (13 marks)

Discuss five approaches to reducing the critical path.

Which is the most effective? And why?

Which is the most difficult to achieve? And why?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!