Question: Question 1: (17 marks) The data given in Table 1 shows PV, EV, and AC values in thousands of dollars for the first 30 weeks
Question 1: (17 marks)
The data given in Table 1 shows PV, EV, and AC values in thousands of dollars for the first 30 weeks of a projects execution before its completion. Answer the following questions:
a. Using three different pen colors, draw a graph showing the curves PV, EV, and AC. Label appropriately the curves and the x-axis and y-axis (5 marks);
b. Indicate the intervals of time where the project is on schedule, going faster or slower than the planned schedule (4 marks);
c. Indicate the intervals of time where the project is on budget, under or over the planned budget (4 marks);
d. Evaluate the budget gain or loss that occurred on week 15 in dollars (2 marks);
e. Evaluate the schedule status on week 25 (2 marks).
| Activity ID | Week Number | PV $(000) | EV $(000) | AC $(000) |
| A | 5 | 7 | 5 | 2 |
| B | 10 | 13 | 10 | 7 |
| C | 15 | 18 | 15 | 12 |
| D | 20 | 20 | 20 | 20 |
| E | 25 | 22 | 25 | 28 |
| F | 30 | 27 | 30 | 33 |
Question 2: (13 marks)
Discuss five approaches to reducing the critical path.
Which is the most effective? And why?
Which is the most difficult to achieve? And why?