Question: Question 1 - [ 18 marks] A company is embarking on a new project in view of improving its competitiveness on the market. An analysis

Question 1 - [ 18 marks]

A company is embarking on a new project in view of improving its competitiveness on the market. An analysis of the different main tasks to be undertaken is tabulated below. The duration, in weeks, of the different tasks.

Activities

Immediate predecessor activities

Duration in weeks

Optimistic

Most likely

Pessimistic

A

-

9

10

17

B

-

6

6

6

C

A

6

8

10

D

A,B

11

12

13

E

B

9

10

11

F

C,D,E

7

10

13

G

C

5

6

7

H

E,F

8

8

8

I

G

6

9

12

J

G

13

15

23

K

F,H

18

18

18

L

I,J

7

10

19

M

L

5

8

11

  1. Using the PERT approach, construct the network diagram for the scheme of activities given in the table including full information (i.e. earliest and latest start times) so as to satisfy the scheduling requirements. (12 marks)
  2. State the critical path and the project completion time. (2 marks)
  3. Determine the variance and standard deviation for the project. (4 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!