Question: Question 1 2 ( 1 point ) Saved A network consists of the activities in the following list. Activity Predecessor Time ( weeks ) A
Question point
Saved
A network consists of the activities in the following list.
Activity Predecessor Time weeks
A
B A
C A
D
E B
F D
G B
H C E
I F G
J H I
If activity E will be delayed by weeks, there will be no impact to the project duration.
Question options:
True
False