Question: Question 1 2 Suppose for a particular project that activity A will take 4 weeks to complete, activity D will take 8 weeks to complete,

Question 12
Suppose for a particular project that activity A will take 4 weeks to complete, activity D will take 8 weeks to complete, and activity E will take 3 weeks to complete. Also, suppose that for this project the critical path is A-D-E. Which of the following statements is true
 Question 12 Suppose for a particular project that activity A will