Question: Suppose for a particular project that activity A will take 4 weeks to complete, activity D will take 8 weeks to complete, and activity E

Suppose for a particular project that activity A will take 4 weeks to complete, activity D will take 8 weeks to complete, and activity E will take 3 weeks to complete. Also, suppose that for this project the critical path is A-D-E. Which of the following statements is true?

a.

The project completion time for this project is 15 weeks.

b.

The project completion time for this project cannot be determined without knowing the predecessors and times for the other activities.

c.

The slack for activity E will be 5 weeks.

d.

The project completion time for this project is 8 weeks, the largest of the activity times on the critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!