Question: Suppose for a particular project that activity A will take 4 weeks to complete, activity D will take 8 weeks to complete, and activity E
Suppose for a particular project that activity A will take 4 weeks to complete, activity D will take 8 weeks to complete, and activity E will take 3 weeks to complete. Also, suppose that for this project the critical path is A-D-E. Which of the following statements is true?
| a. | The project completion time for this project is 15 weeks. | |
| b. | The project completion time for this project cannot be determined without knowing the predecessors and times for the other activities. | |
| c. | The slack for activity E will be 5 weeks. | |
| d. | The project completion time for this project is 8 weeks, the largest of the activity times on the critical path. |