Question: Question 1 ( 3 0 % ) : For the following schedule, draw the AON network, perform the CPM calculations to compute the values of

Question 1(30%):
For the following schedule, draw the AON network, perform the CPM calculations to compute the values of ES, EF, LS, LF, TF, FF for the activities. In the network, also mark the critical path.
\table[[Activity,IPA,Duration (Days)],[A,--,5],[B,A,7],[C,A,10],[D,A,5],[E,A,9],[F,B,6],[G,B, C,4],[H,B, C, D,8],[I,C, D,2],[J,E,5],[K,F,8],[L,E, G,9],[M,F, G, H,7],[N,F, G, H, I,3],[O,H, I,6],[P,M, N, O,4],[Q,K, L,3],[R,L, M,5],[S,J, P,4],[T,Q,6],[U,Q, R,4],[V,T, U, S,1],[,,]]