Question: Question 1 3 0 points The following eight activities constitute an overall bar chart portrayal of a 4 - month project. After 1 . 5

Question 1
30 points
The following eight activities constitute an overall bar chart portrayal of a 4-month project. After 1.5 months, Activities A, B, D, and half of E were completed, for an actual cost of $8,000. Using earned value analysis, evaluate the status of the project by determining the following indicators. State if the project is over or under budget and if it is ahead of or behind schedule.
(30 points =2 points for each indicator and 4 points for the project status summary)
BCWS
BCWP
ACWP
SV
CV
SPI
CPI
BAC
% Complete
ETC
EAC
VAC
TCPI
\table[[Activity,Cost,\table[[Month],[1]],\table[[Month],[2]],\table[[Month],[3]],\table[[Month],[4]]],[A,$2,000,,,,],[B,$1,000,,,,],[C,$6,000,,,,],[D,$2,000,,,,],[E,$7,000,,,,],[F,$9,000,,,,],[G,$3,000,,,,],[H,$10,000,,,,]]
Question 1 3 0 points The following eight

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!