Question: Question 1 3 0 points The following eight activities constitute an overall bar chart portrayal of a 4 - month project. After 1 . 5
Question
points
The following eight activities constitute an overall bar chart portrayal of a month project. After months, Activities A B D and half of E were completed, for an actual cost of $ Using earned value analysis, evaluate the status of the project by determining the following indicators. State if the project is over or under budget and if it is ahead of or behind schedule.
points points for each indicator and points for the project status summary
BCWS
BCWP
ACWP
SV
CV
SPI
CPI
BAC
Complete
ETC
EAC
VAC
TCPI
tableActivityCost,tableMonthtableMonthtableMonthtableMonthA$B$C$D$E$F$G$H$