Question: Question 1 3 ( 4 points ) Instead of creating a detailed schedule for all of the activities required to complete an entire project, agile

Question 13(4 points)
Instead of creating a detailed schedule for all of the activities required to complete an entire project, agile teams focus on the most valuable work they can complete within each iteration using an approach called
a) Scrum of Scurms
b) release planning
c) kanban
d) timeboxing