Question: QUESTION 1 3 The blueprints for the new construction projects have been completed and construction is ready to begin. While the organization was thinking about

QUESTION 13
"The blueprints for the new construction projects have been completed and construction is ready to begin. While the organization was thinking about erecting a modular structure, they decided on a more traditional approach. The foundation will be poured and cured before the framing begins. This is an example of:"
Discretionary dependency
Mandatory dependency
External dependency
Internal dependency