Question: The blueprints for the new construction projects have been completed and construction is ready to begin. While the organization was thinking about erecting a modular
The blueprints for the new construction projects have been completed and construction is ready to begin. While the organization was thinking about erecting a modular structure, they decided on a more traditional approach. The foundation will be poured and cured before the framing begins. This is an example of:
A. Discretionary dependency B. * Mandatory dependency C. External dependency D. Internal dependency
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts