Question: Question 1 (30 points) Complete the following MRP matrix for item A (fill the blue cells): Note: The beginning inventory is shown besides the Projected

Question 1 (30 points) Complete the following MRP

Question 1 (30 points) Complete the following MRP matrix for item A (fill the blue cells): Note: The beginning inventory is shown besides the "Projected on Hand". Period 1 2 3 4 6 7 8 5 60 10 15 25 75 85 45 60 Item: A LLC: 1 Lot Size: Mult 50 LT: 2 Gross Requirements Scheduled Receipts Projected on Hand 50 Net Requirements Planned Order Receipts Planned Order Releases