Question: Question 1 4 2 ptsCLO # 7 : Develop a Preliminary ( conceptual ) Schedule for a Commercial BuildingThe critical path is the longest path
Question ptsCLO #: Develop a Preliminary conceptual Schedule for a Commercial BuildingThe critical path is the longest path in the project network.
True
False
Question ptsCLO #: Develop a Preliminary conceptual Schedule for a Commercial BuildingIf resources are limited the early or late schedules are no longer unique.
True
False