Question: Question 1 . 4 The soil profile at a site is shown in Figure 1 . 4 . ( a ) Determine the total vertical

Question 1.4
The soil profile at a site is shown in Figure 1.4.
(a) Determine the total vertical stresses, pore pressures and effective vertical stresses at points A
and B. The unit weight of water at this site is 10kNm3.
(B: 194,120,74kPa
Rock
Figure 1.4
(b) A fill layer of 4m is to be added to the site. The total unit weights above and below water are
17 and 19kNm3 respectively.
(i) What are the increases in total vertical stress, pore pressure and effective vertical stress
at "B" at the instant of fill placement?
(44,44,0kPa)
(ii) What are the final total vertical stress, pore pressure and effective vertical stress long
time at "B" long time after the fill placement when all excess pore pressure has been
dissipated?
(238,120,118kPa)
(c) If the clay is normally consolidated, what is the future ground settlement due to the 4m of fill
stated above. (Cc=0.68,Cr=0.14,eo=2.16)
(d) If the clay has an average OCR of 1.2, what is the future ground settlement?
Question 1 . 4 The soil profile at a site is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!