Question: QUESTION 1 [40 MARKS] TASK DESCRIPTION A Requirement gathering B Design C Coding D Networking E Security Installation F Integration G Testing H Training I
![QUESTION 1 [40 MARKS] TASK DESCRIPTION A](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/12/67567b8f5d4bb_97467567b8ed4eed.jpg)
QUESTION 1 [40 MARKS] TASK DESCRIPTION A Requirement gathering B Design C Coding D Networking E Security Installation F Integration G Testing H Training I Delivery (a) Determine the critical path of the project [10 Marks] (b) Illustrate the Tasks on a Gantt Chart. [10 Marks] (c) Calculate the planned duration of the project. [10 Marks] (d) Identify and explain any non-critical tasks and the float (free slack) on each. [10 Marks] DURATION (DAYS) 1 3 5 3 6 2 2 1 1 PREDECESSOR/S A B B B C.D E,F G H
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock