Question: Question 1 (45 points). Table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding
Question 1 (45 points). Table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.
Table 1 - Environmental Project Data
| Activity | Normal Time (weeks) | Crash Time (weeks) | Cost to Crash ($ per week) | Immediate Predecessor(s) |
| A | 7 | 6 | 200 | None |
| B | 12 | 9 | 250 | None |
| C | 7 | 6 | 250 | A |
| D | 6 | 5 | 300 | A |
| E | 1 | 1 | - | B |
| F | 1 | 1 | - | C, D |
| G | 3 | 1 | 200 | D, E |
| H | 3 | 2 | 350 | F |
| I | 2 | 2 | - | G |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
