Question: Question 1 (45 points). Table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding

Question 1 (45 points). Table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.

Table 1 - Environmental Project Data

Activity

Normal Time (weeks)

Crash Time (weeks)

Cost to Crash

($ per week)

Immediate Predecessor(s)

A

7

6

200

None

B

12

9

250

None

C

7

6

250

A

D

6

5

300

A

E

1

1

-

B

F

1

1

-

C, D

G

3

1

200

D, E

H

3

2

350

F

I

2

2

-

G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!