Question: Question 1 5 0 . 2 pts Which is NOT correct about work package? It is a short - duration task that has a definite
Question
pts
Which is NOT correct about work package?
It is a shortduration task that has a definite start and stop point, consumes resources, and represents cost.
It is the lowest level of the WBS
It is the basic unit used for planning, scheduling, and controlling the project.
It should be as dependent of other work packages of the project as possible.