Question: Question 1 5 0 . 2 pts Which is NOT correct about work package? It is a short - duration task that has a definite

Question 15
0.2 pts
Which is NOT correct about work package?
It is a short-duration task that has a definite start and stop point, consumes resources, and represents cost.
It is the lowest level of the WBS.
It is the basic unit used for planning, scheduling, and controlling the project.
It should be as dependent of other work packages of the project as possible.
 Question 15 0.2 pts Which is NOT correct about work package?