Question: Question 1 6 3 . 0 3 pts Consider the following project ( assume that normal and crash times are in days, costs in $

Question 16
3.03 pts
Consider the following project (assume that normal and crash times are in days, costs in $).
The slopes of activities B and C are:
\table[[Activity,Normal Time,Normal Cost,Crash Time]] Crash Cost
600 and 500
300 and 600
267 and 400
300 and 333
750 and 1500
600 and 333
500 and 0