Question: Question 1 6 4 ptsIn a bicycle factory, frames are delivered to an assembly station five at a time. It takes 4 3 minutes for
Question ptsIn a bicycle factory, frames are delivered to an assembly station five at a time. It takes minutes for frames to be manufactured and delivered to assembly. Approximately bicycles are assembled each hour and management has decided that of hourly demand should be maintained as safety stock.how many Kanban containers are needed?Round it to two decimal points