Question: Question 1 7 Team Vextech is working in Scrum for the first time and theteam is a mix - of experienced developers and freshers. in
Question
Team Vextech is working in Scrum for the first time and theteam is a mixof experienced developers and freshers. in order to save tim quickly share a release plan with the client, VexTech has asked a few of their team members to do the estimation on Product Backlog a have sutmitted a proposat in terms of man days. Review by the customer suggests that though the estimate looks good on paper, it is fail. Which of the following are ThuE with respect to this scenario?
A Estimates were done in beginning of Scrum project and hence the problem
All the team members of Scrum team should have been involved in estimation
coternat revicw process by a different team should have been followed in release planning
D For release planning team should have gone for retative estimation with a baseline using story points than absolute estimation
B and
and
A cand D
All the given options
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock