Question: Question 3 Team VexTech is working in Scrum for the first time and the teaim is a mix of experienced developers and frechers in order

Question 3
Team VexTech is working in Scrum for the first time and the teaim is a mix of experienced developers and frechers in order to swe tome and quickly share a release plan with the client, VexTech has asked a few of their team members to do the estimation on Product Backlog and they have submitted a proposal in terms of man-days. Review by the customer suggests that though the estimate looks good on paper, it is hikely to fail. Which of the following are TRUE with respect to this scenario?
A) Estimates were done in beginning of Scrum project and hence the problem
(i) All the team members of Scrum team should have been involved in estimation
External revew process by a different team shoud have been followed in release planning
D) For release planning team should have gone for relative estimation with a baseline using story points than absolute estmation
Eand D
A and B
A. Cand D
All the given options
 Question 3 Team VexTech is working in Scrum for the first

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!