Question: Question 1 8 8 points table below lists the activities, activity durations, and immediate predecessors. Draw the network to work this and answer the question:

Question 18
8 points
table below lists the activities, activity durations, and immediate predecessors. Draw the network to work this and answer the question:
Which of the following is the critical path?
\table[[Activity,Time,\table[[Immediate],[Predecessor]]],[A,3,-],[B,8,-],[C,5,A],[D,2,B],[E,5,C,D],[F,8,A],[G,3,C,F],[H,4,E,G]]
A. A-C-E-G
B. A-D-F-G-H
C. B-D-E-H
D. A-C-D-H
 Question 18 8 points table below lists the activities, activity durations,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!