Question: Question 1 8 8 points table below lists the activities, activity durations, and immediate predecessors. Draw the network to work this and answer the question:
Question
points
table below lists the activities, activity durations, and immediate predecessors. Draw the network to work this and answer the question:
Which of the following is the critical path?
tableActivityTime,tableImmediatePredecessorABCADBECDFAGCFHEG
A ACEG
B ADFGH
C BDEH
D ACDH