Question: The table below lists the activities, activity durations, and immediate predecessors. Draw the network to work this and answer the question: What is the duration

The table below lists the activities, activity durations, and immediate predecessors. Draw the network to work this and answer the question:
What is the duration of the critical path?
\table[[Activity,Time,\table[[Immediate],[Predecessor]]],[A,3,-],[B,8,-],[C,5,A],[D,2,B],[E,5,C,D],[F,8,A],[G,3,C,F],[H,4,E,G]]
A)18
B)17
C)15
D)19
 The table below lists the activities, activity durations, and immediate predecessors.