Question: Question 1 A project has 6 activities a, b, c, d, e and f. Their estimated durations are 2, 3, 5, 2, 1 and 7

Question 1 A project has 6 activities a, b, c, d,

Question 1 A project has 6 activities a, b, c, d, e and f. Their estimated durations are 2, 3, 5, 2, 1 and 7 days. A network is drawn and following three paths are identified. Path 1: a-b-f Path 2: a-c-d-f Path 3. a-c-e-f How many days will be required to complete this project? > A Moving to the next question prevents changes to this