Question: A project has 6 activities a, b, c, d, e and f. Their estimated durations are 2, 3, 5, 2, 4 and 7 days. A
A project has 6 activities a, b, c, d, e and f. Their estimated durations are 2, 3, 5, 2, 4 and 7 days. A network is drawn and following three paths are identified.
Path 1: a-b-f
Path 2: a-c-d-f
Path 3. a-c-e-f
How many days will be required to complete this project?