Question: QUESTION 1 A project has been defined to contain the following list of activities, along with the required times for completion as follow: ACTIVITY IMMEDIATE
QUESTION 1
A project has been defined to contain the following list of activities, along with the required times for completion as follow:
| ACTIVITY | IMMEDIATE PREDECESSOR (S) | TIME (DAYS) |
| A | - | 9 |
| B | A | 7 |
| C | A | 3 |
| D | B | 6 |
| E | B | 9 |
| F | C | 4 |
| G | E,F | 6 |
| H | D | 5 |
| I | G,H | 3 |
- Draw the precedent diagram
- Calculate Earliest Finish and Latest Start for activity E till I based on the precedent diagram above.
- By using the information in question 1 (b), identify the critical path.
- By using the information in question 1 (b), determine the project completion time.
- If activity C were delayed by 8 days, what would be the impact on the project completion?
Explain your answer.