Question: QUESTION 1 A project has been defined to contain the following list of activities, along with the required times for completion as follow: ACTIVITY IMMEDIATE

QUESTION 1

A project has been defined to contain the following list of activities, along with the required times for completion as follow:

ACTIVITY

IMMEDIATE PREDECESSOR (S)

TIME (DAYS)

A

-

9

B

A

7

C

A

3

D

B

6

E

B

9

F

C

4

G

E,F

6

H

D

5

I

G,H

3

  1. Draw the precedent diagram

  1. Calculate Earliest Finish and Latest Start for activity E till I based on the precedent diagram above.

  1. By using the information in question 1 (b), identify the critical path.

  1. By using the information in question 1 (b), determine the project completion time.

  1. If activity C were delayed by 8 days, what would be the impact on the project completion?

Explain your answer.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!