Question: Question # 1 : A small project with its activities, relationships, durations in weeks, and needed weekly resources is shown in Figure 1 . 1
Question #:
A small project with its activities, relationships, durations in weeks, and needed weekly resources is shown in Figure It is required to:
Perform the CPM calculations and highlight the critical path.
Determine the project's final duration if there are only units of resources per week.
Draw the bar chart for the baseline schedule if there is no Deadline to respect.
Figure : Project's activities, relationships, durations, and needed resources