Question: Question 1. An assembly line with nine tasks is to be balanced. The longest task is 9 minutes, and the total time for all
Question 1. An assembly line with nine tasks is to be balanced. The longest task is 9 minutes, and the total time for all tasks is 45 minutes. The line will operate for 448 minutes per day. Round up your answers to the nearest whole number (40 points, 10 points each). See Lecture M4-2 for details. a. What are the minimum output rates? 50 b. What are the maximum output rate? c. What cycle time will provide an output rate of 30 units per day? d. What is the minimum number of workstations needed if the output rate needed was 30 a day? 10 1.5 30