Question: Question 1: Draw the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish
Question 1: Draw the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resources Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now? Show ALL of your working to get the points ( 15pts). Develop a looding schedule for each resource below. Fill in the times below for a resoure activity schedule